Mumbai: Just 68-km roads concreted this year, official data shows
Updated On: 31 July, 2023 06:47 AM IST | Prajakta Kasale
At this rate, it will take roughly 15 years for BMC to build concrete roads for all of Mumbai, while it promised high court it will do this in 2 years
A road being concreted near Mantralaya in February. Pic/Atul Kamble
Despite the tall claims of the chief minister and assurances from the BMC, the concreting of roads is going on at a snail’s pace with only 68 km of roads completed in the past 12 months. But this was not the picture before. Interestingly, the BMC had concreted on an average 150 km roads annually in the past few years.
The delayed rain saved the Brihanmumbai Municipal Corporation's (BMC) image in June. But as the rain showed its full glory in mid-July, the roads in Mumbai turned into the lunar surface. The same old story of pothole-riddled roads repeated. Last year, the BMC faced the peoples' wrath for the bad state of roads across the city and in July 2022, Chief Minister Eknath Shinde promised that they would concrete every road in the city within two years.
UNLOCK FULL ACCESS
Buy now to read the full story.
For just ₹29/-
Already a member? Login
For any queries please contact us: E-mail: support@mid-day.com
Trending Stories
Latest Web Stories
Latest Photos
17 December, 2025 11:56 AM IST | IN PHOTOS: MLAs at Vidhan Bhavan during Maharashtra Legislative Council polls
Asif Ali Sayed
09 September, 2024 09:32 PM IST | IN PHOTOS: People in Mumbai celebrate Gauri Puja during Ganeshotsav
Asif Ali Sayed
09 September, 2024 09:13 PM IST | IN PHOTOS: Mumbai witnesses sunny weather as rains take a break
Asif Ali Sayed
09 September, 2024 01:53 PM IST | In Photos: Amit Shah attends Ganeshotsav 2024 festivities in Mumbai
Divya Nair
Latest Videos
ADVERTISEMENT
Mid-day Fast
Latest Headlines
14 July, 2026 04:05 PM IST | mid-day online correspondent
14 July, 2026 11:32 AM IST | Bespoke Stories
10 July, 2026 02:40 PM IST | Makepeace Sitlhou